Upgrading a grid supply point
Freedom delivered the design and build of the Abernethy Grid Supply Point (GSP) upgrade in Perthshire, Scotland, for Scottish and Southern Electricity Networks (SSEN). The project replaced two 60MVA transformers with two 120MVA units, including their testing and commissioning. We also supplied, tested and commissioned all the associated 132kV and 33kV plant and infrastructure. The civils package covered plant and equipment foundations, the substation extension platform, road and fencing.
Delivering through disruption
The design and procurement of key materials took place during ongoing global Covid-19 restrictions and the war in Ukraine. The project also had to meet a high standard under SSEN's scrutiny, work to planned strategic outage dates, and have the right resource available when needed. Multiple subcontractors, both Freedom's and SSEN's, were on site at the same time. Working with local residents to maintain good relationships and reputation was a priority throughout.
Outcome
The works were completed on time and to a high standard. SSEN and local stakeholders were happy with the project.
Key benefits and stats
Client: SSEN
Type of work: Substation design, procurement, build, test and commissioning
Sector: New connections
Contract: Fixed price
Duration: 85 weeks (2021–2023)
Voltage: 132kV / 33kV
2 × 60MVA transformers replaced with 2 × 120MVA units
Full design and build, including civils, plant and commissioning
Delivered through Covid-19 and Ukraine-related supply constraints
Completed to a high standard, with SSEN and local stakeholders satisfied