Abernethy Grid Substation Upgrade, Perthshire

Posted: 20 November 2026
Reading Time: 3 minutes

Doubling transformer capacity at a key grid substation, delivered through global supply chain disruption.

  • SSEN Abernethy Substation

Upgrading a grid supply point

Freedom delivered the design and build of the Abernethy Grid Supply Point (GSP) upgrade in Perthshire, Scotland, for Scottish and Southern Electricity Networks (SSEN). The project replaced two 60MVA transformers with two 120MVA units, including their testing and commissioning. We also supplied, tested and commissioned all the associated 132kV and 33kV plant and infrastructure. The civils package covered plant and equipment foundations, the substation extension platform, road and fencing.

Delivering through disruption

The design and procurement of key materials took place during ongoing global Covid-19 restrictions and the war in Ukraine. The project also had to meet a high standard under SSEN's scrutiny, work to planned strategic outage dates, and have the right resource available when needed. Multiple subcontractors, both Freedom's and SSEN's, were on site at the same time. Working with local residents to maintain good relationships and reputation was a priority throughout.

Outcome

The works were completed on time and to a high standard. SSEN and local stakeholders were happy with the project.

Key benefits and stats

  • Client: SSEN

  • Type of work: Substation design, procurement, build, test and commissioning

  • Sector: New connections

  • Contract: Fixed price

  • Duration: 85 weeks (2021–2023)

  • Voltage: 132kV / 33kV

  • 2 × 60MVA transformers replaced with 2 × 120MVA units

  • Full design and build, including civils, plant and commissioning

  • Delivered through Covid-19 and Ukraine-related supply constraints

  • Completed to a high standard, with SSEN and local stakeholders satisfied