Open Nav

23 Oct 2020

Success in the Constructing Excellence Yorkshire and Humber Awards

We’re delighted to take the Offsite Construction award for our work on the University Hospital of North Tees Energy Centre project.

The Energy Centre at the University Hospital of North Tees was a £14m project which saw NG Bailey complete a Principal Contractor role to overhaul the hospital’s energy supply as part of the Trust’s ongoing Sustainability and Transformation plan. 

It involved the creation of a brand new services infrastructure and energy centre to give the hospital a more reliable supply and reduce their energy consumption and carbon footprint. All the work was completed without causing any disruption to the on-going operation of the hospital and patient safety was maintained at all times.

To remove the most labour-intensive works from the hospital site, major elements of the internal services were manufactured off-site, at our specialist assembly facilities in Bradford, saving more than 5,000 hours of labour on the site and reducing health and safety risks.

Partner
Partner
Partner
Partner
Partner
Partner